The first sod is cut as the building of our new school gets under way.

Thursday, 2 October 2008

Nursery Foundations.


Great relief for Mrs Gregory and all in our Nursery as the foundations to the new nursery are started.

Wednesday, 1 October 2008

P5,6 and 7 floors complete.


In the foreground is what will be the main entrance to the school. (You can just see the corner of my office. )To the left are the P5, P6 and P7 classrooms. The playground will be to the rear of the school.

Foundation Stage Foundations!


Stacks of block ready to be built on the foundations of the P1 & P2 classrooms.

P7 classrooms


This shows the layout of the two P7 classrooms. The areas not concreted are the cloakrooms and toilets for each of the classrooms.

More Floors


More Floors



A close up showing how the concrete is transferred from one vehicle to another and then pumped to wherever needed.

Laying the floors.


The photograph shows the concrete being pumped to the areas required. The lorry arrived at 5.30am and work continued all day.